Koper, Slovenia (Ports Europe) January 19, 2022 – A consortium led by Kolektor CPG has completed the digging works on the first kilometre of tunnels along the second track of the Divaca-Koper railway line. Excavation lengths are: 1. Lokev tunnel (T1-DI): main pipe 150 meters, service pipe 110 meters 2. Mlinarji tunnel (T7-KP): 362 meters….